Installation design for EC Inowrocław and EC Janikowo

Sweco Engineering designers faced new challenge. This time, at the request of Sirius Poland for the company CIECH Soda Poland, we prepared construction project of denitrification installation (SCR) and the flue gas desulphurization installation (FGD) for EC Inowrocław and construction project of the flue gas desulphurization installation (FGD) for EC Janikowo. Everything is done to reduce emission from combustion of fuels.

Key facts

Project name: Construction project of denitrification installation (SCR) and the flue gas desulphurization installation (FGD) to reduce emission from combustion of fuels.

Location: EC Inowrocław and EC Janikowo

Client: Sirius Polska dla CIECH Soda Polska

Project start ECI: August 2015

Construction works start ECI: November 2015

Completion ECI: June 2017

Project start ECJ: December 2015

Construction works start ECJ: April 2016

Completion ECJ: September 2017

Project description

The investments are designed to adapt combustion installations at EC to the emission requirements laid down in the "Directive of the European Parliament and of the Council 2010/75/EU of 24 November 2010. On industrial emission (integrated pollution prevention and control)."

"Our specialists in the design process took into account the environmental and social aspect of the project. We used all the available means to ensure that the installations will help to improve air quality by reducing emission of pollutants from combustion of fuels." - says Wojciech Pietruk, Construction Team Manager at Warsaw office Sweco Engineering.

The realization of the project on a global level provides an international team of engineers, the best professionals in their respective industries, as well as the latest design technology BIM.

Our specialists from the Sweco Enginieering in cooperation with Valmet Technologies Oy and Sirius Engineers Ltd. are responsible for the development of complete technical documentation (building permit design, basic design and execution design in all industries), together with obtaining all the formal and legal permits required for the commissioning of the installation.

Design works for EC Inowrocław started in August 2015, construction works began in November 2015 and the planned completion date of the project is June 2017. We are currently working on the execution design.

Design works for EC Janikowo started in December 2015, construction works began in April 2016 and the planned completion date of the project is September 2017. We are currently working on the execution design.