Sweco Engineering designers faced new challenge. This time, at the request of Sirius Poland for the company CIECH Soda Poland, we prepared construction project of denitrification installation (SCR) and the flue gas desulphurization installation (FGD) for EC Inowrocław and construction project of the flue gas desulphurization installation (FGD) for EC Janikowo. Everything is done to reduce emission from combustion of fuels.
Project name: Construction project of denitrification installation (SCR) and the flue gas desulphurization installation (FGD) to reduce emission from combustion of fuels.
Location: EC Inowrocław and EC Janikowo
Client: Sirius Polska dla CIECH Soda Polska
Project start ECI: August 2015
Construction works start ECI: November 2015
Completion ECI: June 2017
Project start ECJ: December 2015
Construction works start ECJ: April 2016
Completion ECJ: September 2017